The Fraser Highway One-Way Utilities and Public Realm Project will enhance the experience for our businesses, residents, and visitors.

This project focuses on upgrading the aging underground infrastructure that needs to be replaced while revitalizing the Fraser One-Way. The improvements will create more greenerynew community gathering spaces, and enhanced pedestrian amenities 
for all.


 

Phase 1 Work Progress

  • Installation of BC Hydro and City-owned underground storm sewer infrastructure is ongoing and anticipated to continue through February
  • Wayfinding signage has been installed to help inform community members that businesses are open during construction  

ONGOING WORKS:

 BC Hydro underground infrastructure                       City-owned storm sewer infrastructure

WAYFINDING SIGNAGE:

Feeback Requested - Parking Strategy

Langley City is developing a Parking Strategy to improve parking in the City and prepare for future growth, ensuring that residents, workers, businesses and visitors have fair and dependable access to parking options. 

The Parking Strategy will focus on the Nicomekl and Douglas Neighbourhoods, specifically Downtown Langley, the Brydon Park area, and the Michaud Crescent area.  

Take the survey to help shape the future of public parking in Langley City to be entered to win a $50 VISA gift card. It takes 5 to 10 minutes to complete the survey, which is open until March 9, 2025. 

Note:

  • Limited off-street parking is available between Salt Lane and 206 Street.

  • Construction will generally occur during the daytime based on the City's Noise Control Bylaw. Some work may occur on weekends or at night; however, noisy construction activities will not be permitted during night work. 

  • Vibrations are to be expected during construction. 


 

Businesses are open

While we navigate through this transformative period, access to businesses along the Fraser Highway One-Way will be maintained, meaning you can access these businesses through their front door

Safe passage of pedestrians and vehicles will be facilitated by the use of traffic control signage and personnel during construction hours.

 

Parking is available!

  • Free parking will be available throughout the Fraser Highway One-Way in a phased approach.
    • Phase 1 - Limited off-street parking available between January to April 2025
    • Phase 2 - Limited off-street parking available between May to August 2025
  • 37 free parking stalls are available at Langley City Hall (20399 Douglas Crescent)
  • 10 parking signs have been posted in the area to advise community members of available parking locations. New additional signage for added clarity is currently being explored and developed

 

Business Resources


 