Alder-Webb Connector
Construction is underway on this connector road. This project will include paving, drainage, water main, street trees, streetlights, curb and sidewalk works.
Council approved 20 locations for rapid rectangular flashing beacon crosswalks. Installations will include Watson Road at Watson Elementary, Yale Road at Carleton, and more.
Work has begun on the 2020 program. Roads paved so far include Bernard Avenue from Ashwell to Railway, No. 5 Road from Boundary to Stewart, and major patching on Keith Wilson Road.
The City and the Ministry of Transportation and Infrastructure are working together on the Phase 2 design, which is scheduled for construction in summer 2021.